Previous episode The inside view: why a project plan only shows the way things go right

The planning fallacy: why projects usually take longer than the estimate

Unknown unknowns: why many small risks make a project delay likely

Ten small steps, each with only a small chance of going wrong: a project plan like that looks safe. Do the sum, and a delay is more likely than not. And the worst surprises are on no list at all.

  1. 1 You look at each step of the delivery app on its own. Could this one go wrong? Hardly, you think: maybe one chance in ten. So no step gets extra time.your plan: 10 stepsyouEach onelooks fine.

    You look at each step of the delivery app on its own. Could this one go wrong? Hardly, you think: maybe one chance in ten. So no step gets extra time.

  2. 2 But the plan holds only if all ten steps go right. With nine chances in ten for each, that happens only about one time in three. A long chain of likely steps is an unlikely chain.the same plan, three timeson timelatelateexample numbers

    But the plan holds only if all ten steps go right. With nine chances in ten for each, that happens only about one time in three. A long chain of likely steps is an unlikely chain.

The rest of this episode is for subscribers

Subscribe to read every premium episode. You can cancel when you want.

Paid yearly: $99 instead of $119.88

Next episode Why delays in a project add up, while time saved early gets lost

Share this comic

More comics