Previous episode A famous study of the planning fallacy: even the worst-case estimate was too short

The planning fallacy: why projects usually take longer than the estimate

The inside view: why a project plan only shows the way things go right

You plan a project step by step, and every step plays out in your head the way you planned it. Psychologists call this the inside view, and it pulls every estimate toward the best case.

  1. 1 You picture the delivery app step by step: the map page, the driver's screen, the messages to customers. Three weeks, your list says.your planmap page4 daysdriver's screen3 daysmessages3 daysseven more steps5 days3 weeksexample numbersyou

    You picture the delivery app step by step: the map page, the driver's screen, the messages to customers. Three weeks, your list says.

  2. 2 Each step plays in your head like a short film, and in each film, the step goes the way you planned. That's what a plan is: a story of the steps you can see, going right.map pagedriver'sscreenmessagesyou

    Each step plays in your head like a short film, and in each film, the step goes the way you planned. That's what a plan is: a story of the steps you can see, going right.

  3. 3 Looking at a project from inside its own plan has a name: the inside view. Kahneman and his colleague Dan Lovallo gave it that name in 1993.your planyou???the inside view

    Looking at a project from inside its own plan has a name: the inside view. Kahneman and his colleague Dan Lovallo gave it that name in 1993.

  4. 4 None of the surprises that made the cake app late were in your plan, and some you could not have listed at all. So how can an estimate make room for problems nobody can picture yet?the cake app plancake menuorder formpaymentpaymentcheckoldphonesnewcakes

    None of the surprises that made the cake app late were in your plan, and some you could not have listed at all. So how can an estimate make room for problems nobody can picture yet?

  5. Go further

    An older name for the same thing.internal approachwhat Kahneman andTversky called it in1979: guessing fromthe plan of the casein front of you

    An older name for the same thing.

Next episode Unknown unknowns: why many small risks make a project delay likely