The planning fallacy: why projects usually take longer than the estimate

Why you give a project too little time, even after being late before

Your last project ran late, and you know it. You plan the next one with care, and it runs late again. The trap is called the planning fallacy, and almost everyone falls into it.

  1. 1 Miva runs a small bakery, and her phone rings all day with cake orders. You and Rono build apps for small shops, so she asks you for one, and how long it will take.MivaAn app forcake orders: howlong will it take?youRono

    Miva runs a small bakery, and her phone rings all day with cake orders. You and Rono build apps for small shops, so she asks you for one, and how long it will take.

  2. 2 You list the work, give each task a few days, and add them up: ten working days. "Two weeks," you tell her. That number is your estimate.your plancake menu2 daysorder form3 dayspayment3 daysemail to the bakery1 dayput it online1 day10 daysexample numbersyouTwo weeks!

    You list the work, give each task a few days, and add them up: ten working days. "Two weeks," you tell her. That number is your estimate.

  3. 3 It takes five weeks. Nothing terrible happened: the payment company had to check the bakery before it took card payments, the form broke on old phones, and Miva added new cakes. Each surprise cost a few days.your estimate2 weekshow long it took5 weekspaymentcheckoldphonesnewcakesexample numbers

    It takes five weeks. Nothing terrible happened: the payment company had to check the bakery before it took card payments, the form broke on old phones, and Miva added new cakes. Each surprise cost a few days.

  4. 4 The odd part is that you knew. Your last app, for a flower shop, also took twice as long as planned. But this time, the plan looked so clear.your last app: a flower shopplanned: 3 weekstook 6 weeksyouThat one ranlate too!

    The odd part is that you knew. Your last app, for a flower shop, also took twice as long as planned. But this time, the plan looked so clear.

  5. 5 Guessing too little time for your own work, while you know that similar work ran late, has a name: the planning fallacy. The psychologists Daniel Kahneman and Amos Tversky named it in 1979.what you knowflower shop: 6 weekscake orders: 5 weekswhat you plan nextshort againthe planning fallacy

    Guessing too little time for your own work, while you know that similar work ran late, has a name: the planning fallacy. The psychologists Daniel Kahneman and Amos Tversky named it in 1979.

  6. 6 Miva loves her app, and she already wants a second one, for deliveries. You take a fresh sheet and start a new list.MivaNow an appfor deliveries!you

    Miva loves her app, and she already wants a second one, for deliveries. You take a fresh sheet and start a new list.

  7. Go further

    Two more names, if you want to look further.optimism biasexpecting things to gobetter than theyusually do. The planningfallacy is optimismbias about timeDaniel Kahnemanone of the two whonamed it. Nobel Prizein economics, 2002,for his work on howpeople judge and decide

    Two more names, if you want to look further.

Next episode A famous study of the planning fallacy: even the worst-case estimate was too short